| |
Bricklaying
is an exacting job. It is heavy work, but, most of all, bricklaying
takes lots and lots of patience because it is an exacting craft.
As a do-it-yourselfer, laying bricks is within your skills. If you
have never tackled a bricklaying project before, your first attempt
ought to be a fairly simple job-such as a retaining wall or fence.
This How-To Article addresses "vertical bricklaying" (walls and
fences) rather than "horizontal bricklaying" (patios, walkways,
driveways, etc.).
BRICKLAYING
TERMINOLOGY:
Every craft has its special terminology. Bricklaying is no exception.
Many basics discussed in this Article will be easier to follow if
you learn these terms:
- STRETCHER-
When a brick is laid so that along, narrow side is the one that
is exposed, that brick is said to be a stretcher. The long edge
is horizontal.
- HEADER-
A header brick is laid so that a small end is exposed and the
wide edge is horizontal.
- ROWLOCK
STRETCHER- A stretcher lay so that the long, wide face is
exposed.
- ROWLOCK
HEADER- A header lay so the narrow edge of the face is horizontal.
All masonry walls should be laid on a concrete footing or foundation-except
in the most temperate climates. Foundation is wider than wall.
- SOLDIER-
A brick is called a soldier when it stands vertically with the
narrow, long face exposed.
- SAILOR-
A sailor also stands on end. However, the long, broad face is
exposed.
- WYTHE-
A wythe is the term for all the vertical courses together. A brick
wall may be one, two, or three wythes thick for most purposes.
- CLOSURE
BRICK- In any course, bricks are laid from the outer edges
in toward the center. The final brick, the one that fills the
opening to complete the course, is called a closure brick. This
brick almost always has to be cut to fit properly in its niche.
PREPARATION:
THE FOOTINGS:
Brick structures must be supported by concrete footings. Otherwise,
the heaving ground due to moisture and frost will crack the structure.
Footings should extend to below the frost line. If the wall is load-bearing,
the footing must be as deep as the wall is wide. The width of the
footing should be twice the width of the wall. This means that a
brick wall that is 12 inches thick requires a footing that is 12
inches deep and 24 inches wide. Walls that are not load-bearing
don't have to be as thick or wide. A 2-wythe-thick wall would be
8 inches thick and require a footing 12 to 16 inches wide and 18
inches deep (this is an example). 1 x4 2x4
A simple
trench may be dug for the footing. Or, you may want to dig a trench
and form the sides of it with boards for the footing. This is recommended
since the top of the concrete surface must be leveled. With board
forms, you can use a 2x4 strike on the edges of the forms to level
the concrete between them.
Also,
you can mix the concrete for the footing, or you can prepare the
trench/forms and have a ready-mix truck place the concrete for you.
A good foundation mix, if you do it yourself is 1 bag of cement
to 3-4 bags of aggregate (sand/gravel).
Batter
boards are set after outline of project is determined. Batter boards
are two long crosspieces nailed to stakes driven parallel to each
wall side. There must be a batter board on each side of each corner
of the work. Normally, the batter boards are set about 6 feet back
from the preliminary outline stakes to insure that they are not
knocked down during excavation. String lines from outline stakes
are extended to batter boards. Nails are driven into the top of
the boards and the string lines hook to these nails. Plumb bob dropped
from the intersection of the string lines should fall on top of
the center nails of the outline stakes for wall.
|